What the overlay project is, in 5 minutes
01What an overlay is
An overlay is any piece of UI that appears on top of a webshop page rather than being part of it: a modal asking you to confirm emptying your cart, a side panel to pick a branch, a toast confirming a product was added, a tooltip or popover explaining a price. They show up on every page type and across all Rexel banners.
02Why this project exists
Today most overlays are still legacy: they are built and served by Hybris, the e-commerce platform the webshop is moving away from, and each one has its own look and business rules. The project rebuilds every overlay as an Angular component using our design system (Elektra), the shared library of components and styles that makes every screen look and behave the same. It also moves the data each overlay depends on off Hybris onto the Microservices (MS) platform.
Deliver one core overlay solution for all banners, built on our design system, so customers enjoy a consistent experience across the entire webshop.
03Two tracks, run independently
Every overlay is really two migrations that move at their own pace. That is why the hub has two separate tracking tools for the same list of overlays.
Front-end migration
These phases repeat for each overlay, wave by wave, until the last one is migrated.
- Discovery
- Implementation
- Integration
- Pilot activation
- Global activation
Tracked in the Overlay Roadmap.
Backend migration
Each data call an overlay makes to Hybris moves to the microservices, until the overlay no longer depends on Hybris.
- Endpoint analysis
- MS / bff-web development
- Overlay connected to MS
- Hybris call retired
Tracked in the Back Migration Tracker.
An overlay can be Wave 1 on the front and Blocked on the back at the same time. That is not a contradiction, it is the reason the two tools exist.
04Waves and priorities
We do not migrate all overlays at once. Each one is scored on three criteria, and the result decides which wave (batch of delivery) it lands in.
| Score | What it measures | Weight |
|---|---|---|
| Priority | Business value, customer journey, conversion impact, frequency, visibility, integration risk | 50% |
| Readiness | Lead country validation, implementation risk, test coverage | 30% |
| Page Priority | Which page it lives on | 20% |
05How one overlay gets to production
- Build
- →
- QA, all banners
- →
- UAT pilot
- →
- UAT all banners
- →
- Prod pilot
- →
- Prod other banners
- →
- Pilot activation
- →
- Global activation
- →
- Maturity (legacy clean-up)
The pilot country goes first and is where the PO signs off (highlighted stages). Other banners follow once the pilot is validated, with automated and non-regression tests covering them in UAT. Exceptions apply to overlays that are banner-specific.
The Angular overlay and the Hybris trigger are two independent switches, so QA can test the new overlay end to end before either is turned on for real users. Production config flips happen at end of day, not mid-day.
Full detail, including testing process and open items: Overlay Lifecycle.
06The five tickets behind every overlay
| Ticket | Purpose |
|---|---|
| Legacy analysis | Documents the legacy business rules before any code is written |
| Implementation | Builds the Angular overlay on the Elektra DS |
| Integration | Wires it into the page and its data |
| Hybris config | Trigger / enable-disable config, only if the overlay is Hybris-triggered |
| Clean-up | Retires the legacy path once the new overlay is stable everywhere |
07Where to find what
Overlay Roadmap
Which wave is this overlay in, what is its front-end status, and why is it prioritised the way it is?
Back Migration Tracker
Is the backend of this overlay migrated to MS, and if it is blocked, why and on which endpoint?
Spring Overlay Coverage
Does this overlay have all five tickets in Jira yet?
Overlay Lifecycle
What has to be true before an overlay moves from QA to UAT to production?
Overlay Org Chart
Who is on the project, what is their role, and who do I ask about a given topic?
08Glossary
| Banner | One Rexel webshop brand in one country (for example AUS is Austria Schacke, AUR is Austria Regro). |
| Hybris | SAP Commerce, the legacy e-commerce platform the old overlays and many endpoints live on. |
| Elektra DS | Rexel's Angular design system; new overlays are built from its components (Modal, Side Panel, Toast...). |
| MS | Microservices, the target backend replacing Hybris endpoints. |
| bff-web | The backend-for-frontend layer the web calls; it fronts the MS APIs. |
| Wave | A delivery batch of overlays, ordered by score. |
| Non-sprintable | Not schedulable into a wave yet, usually because the design is not ready. |
| Lead country validation | Sign-off from the lead country that the overlay's scope and rules are right; required for Wave 1. |
| UAT / NRT | User acceptance testing / non-regression testing. |
| Maturity | Final lifecycle stage: new overlay live everywhere, legacy path removed. |